In Vietnam, Standing Deputy Prime Minister Pham Gia Tuc has pressed for immediate measures to tackle challenges hindering the Ho Chi Minh City tidal flood control initiative. During discussions with city officials and key ministries, he highlighted the necessity of executing and operationalizing the project by 2026.
Significant Project Aimed at Protecting Residents
This flood mitigation endeavor will address tidal flooding over an area of around 570 square kilometers in Ho Chi Minh City. Upon completion, it is expected to serve approximately 6.5 million citizens with a network of tidal gates and embankments constructed alongside the Saigon River.
Construction Approaches Completion
City officials report that the investor, Trung Nam Group, has accomplished over 93 percent of construction tasks. The structural work is largely finalized, while the mechanical systems, control tools, landscaping, and auxiliary infrastructure are currently in the last stages of development.
Payment Disputes Causing Delays
Officials have indicated that payment method disagreements and challenges in securing funding have impeded the project's final phases. These financial disputes have raised alarms regarding the feasibility of adhering to the intended completion timeline, despite significant construction advancements.
Legal Framework Affirmed by Ministries
Representatives from various ministries and governmental bodies concurred that there is a substantial legal framework supporting payments outlined in the Build-Transfer contract. They stressed the necessity for the city administration and the investor to finalize a payment strategy that aligns with legal standards and contractual obligations.
Investor Vows to Expedite Project Completion
The investor has confirmed that post-resolution of payment issues, the remaining tasks can be finalized swiftly, with the system potentially operational in 60 days. Furthermore, the company announced an extended warranty on construction spanning three years.
Government Insists on 2026 Timetable
At the meeting's conclusion, Deputy PM Pham Gia Tuc reiterated the necessity of finishing the project by 2026, in accordance with directives from Vietnam's leadership. He tasked the Ho Chi Minh City People's Committee to rapidly finalize the payment strategy to avert any further delays to the project's completion.
Casualties Mount in Lebanon as Israeli Airstrikes Persist Amid Fragile Ceasefire
Lebanon says 4,175 people have been killed and over 12,000 injured since Israeli attacks began in Ma
Sprinkler Malfunction Interrupts World Cup Match at Gillette Stadium
A sprinkler malfunction at Gillette Stadium caused a water leak during halftime of the Iraq vs Norwa
Kyiv’s Historic Monastery May Need Two Years for Full Restoration After Strike Damage
Kyiv’s historic Pechersk Lavra monastery suffered major damage in a recent attack, and repairs could
Vozinha Becomes World Cup Hero After Spain Masterclass
Cape Verde goalkeeper Vozinha stunned Spain with a brilliant display in a historic World Cup draw, g
India A-Sri Lanka A Clash Sparks Vaibhav Controversy
Young India A batter Vaibhav Sooryavanshi was involved in a heated altercation after Sri Lanka A's S
Rashmika's Sweet Gesture For Vijay Goes Viral Online
Rashmika Mandanna was seen helping Vijay Deverakonda during a scholarship event in Telangana, sparki